Flinders Wharf Cooling Tower Upgrade with Strict Safety Compliance

FlowMatrix recently completed a crucial cooling tower upgrade for Premac Airconditioning Pty Ltd at Flinders Wharf, Victoria, by installing a new water distribution box to ensure efficient operation.

Project Details:

Client

Premac Airconditioning Pty Ltd

Project Status

Complete

Job Type

Installation of new water distribution box

Year Completed

2025

Project Overview

FlowMatrix completed a crucial upgrade for Premac Airconditioning Pty Ltd at Flinders Wharf, Victoria.

The project involved the installation of a new water distribution box, a vital component to ensure efficient and reliable cooling tower operations.

Our team arrived on-site prepared to execute the task safely and efficiently. The first step involved completing all necessary site permits and conducting a thorough Job Safety Analysis (JSA) to guarantee a secure working environment. Once approvals were in place, we loaded the site with all required materials and equipment. Safety was prioritised from the outset: the cooling tower was isolated, and personal locks and tags were applied to prevent any accidental activation during the work.

The Workflow: From Arrival to Completion

Execution of Installation

The existing drift eliminators were carefully removed and set aside, ensuring no damage during the process. The old water distribution box was then detached and properly disposed of off-site, making way for the new installation.

The new distribution box, coated with RepelCoat Rapid for enhanced corrosion resistance, was installed meticulously. Following this, we fitted new spray arm grommets to ensure proper operation and sealing.



Project Success

Final Steps and System Testing

With the new components in place, the drift eliminators were reinstalled, restoring the cooling tower to its operational configuration. The system was then de-isolated, and our team conducted a thorough check to verify correct operation and system integrity.

Once confirmed, the site was cleaned up, and all equipment and materials were packed away. The project was finalised with the closure of permits and completion of all safety documentation.

Committed to Safety and Quality

FlowMatrix prides itself on maintaining the highest safety standards and delivering quality workmanship on every project. From planning to completion, our team ensures safe procedures and reliable results.

Connect with us today to explore how our expertise can deliver a precise solution for your requirements.



Gallery

Loading…

Request a Quote

Get in touch – we’re here to answer your questions and provide the support you need.

"*" indicates required fields

This field is for validation purposes and should be left unchanged.